Notice of Works
Contractor Management
Contractor Requirements
Planning maintenance, repairs, fit-out works, signage installation or construction works within your tenancy?
Adelaide Airport is a live operational environment, which means additional approvals, permits, access requirements and safety controls may apply before works can commence.
This page provides everything you need to understand contractor requirements at Adelaide Airport, including approvals, security access, inductions, permits and operational obligations. Early planning is strongly recommended to ensure works can be completed safely, efficiently and with minimal disruption to airport operations, customers and neighbouring tenants.
Approvals & Permits
Understand approval pathways, permits, isolations and airport works requirements.
Security Access
Arrange ASICs, VICs and security access for contractors.
Safety & Inductions
Understand induction, SWMS, PPE and contractor responsibilities.
Airspace & High-Risk Works
Requirements for cranes, rooftop works and activities affecting protected airspace.
Detailed Requirements
- Building Applications
- Airport Works Approvals
- Permit to Work requirements
- Operational approvals
- Access approvals
- After-hours approvals
Contractors working within Sterile Areas or Security Restricted Areas must hold the appropriate security pass.
Where a contractor does not hold a valid ASIC:
- A VIC may be required
- VICs must be organised in advance
- VIC holders must be escorted by an ASIC holder
- Security screening requirements apply
In most cases, tenants are responsible for arranging contractor access requirements, for more information visit: Access & Security Information
- Complete required inductions
- Follow Adelaide Airport Site Rules
- Wear appropriate PPE
- Provide SWMS where required
- Operate safely within public areas
- Report hazards and incidents immediately
Activities Requiring Additional Controls
- Electrical works
- Hot works
- Fire system works
- Communications works
- Confined space entry
- High-risk construction activities
Isolation Requirements
- ARA Fire
- 7-day notice
- Isolation fees
- Permit lead times
Planning Ahead
High-risk isolations generally require a minimum of 7 days' notice and may incur attendance costs.
Related Resources
Asset Details Template
If works involve airport-owned assets, you must inform your Property Manager
Examples include:
- Mechanical equipment
- Fire systems
- Electrical infrastructure
- Building services
- Security infrastructure
- Fixed plant and equipment
Additional Approvals May Be Required For:
- Cranes
- Elevated work platforms
- Rooftop works
- Temporary structures
- Activities affecting protected airspace
Operational Requirements During Works
- Maintain safe pedestrian access
- Keep work areas clean and safe
- Protect customers, staff and neighbouring tenants
- Use approved barriers and hoardings
- Minimise noise, dust and disruption
- Remove waste promptly
- Comply with airport directions
- Use MobileDOCK where required
- Use approved loading zones
- Follow designated delivery routes
- Avoid obstructing passengers or operations
- Remain within approved work areas
- Display security credentials
- Comply with screening requirements
- Secure tools and equipment
- Never share security passes
Important
Unattended tools, equipment or materials may trigger a security response and could result in delays or additional costs.
Emergency Procedures
Stop work immediately
Follow directions from Airport staff or Emergency Services
Evacuate if instructed & Proceed to the designated assembly area